This guide explains how to become ready for monitoring your element production by creating production plan entries in advance.
How to add a production entry
- Click onĀ Production PlanĀ in the menu
- Click onĀ Add production entryĀ in the upper right corner
- Fill out the pop-up box
- Check that the target strength matches the desired strength
- Click onĀ āSave changesā
The production plan entry have now been added to the Production Plan.
How to edit a production entry
- Click onĀ Production PlanĀ in the menu
- Find the production entry you want to edit and click onĀ Details
- You can now edit the āProduction dateā, āLabelā, āWorkstationā and āNotesā
- You canāt edit the āProduction IDā and āCompoundā. If you made a mistake, add a new monitoring and remove the old one
- Click onĀ Save changes
Remove a production entry
- Click onĀ Production PlanĀ in the menu
- Find the production entry you want to remove and click onĀ Remove
- Confirm the removal by clicking onĀ RemoveĀ in the pop-up box